An ambitious and delicate project that involved the Transpack team in the last months: we are talking about the creation of a special packaging able to contain and support a 100-ton industrial machinery.
For the execution, a load-bearing crate with a mixed wood – iron base was designed to hold the machine, for which about 4500 kg of iron were used.
The construction phase of the wood crate was carried out simultaneously with the construction of the machinery in the various phases, an aspect that involved a close collaboration with the client, in order to be able to acquire the information necessary.
The completion of the order also included the coordination of the logistics operations up to the port of Genoa, demonstrating, once again, the Transpack skills in offering a 360 °, effective and highly qualitative service.
The lead time of the entire project was approximately 7 months, from January to July.